<heading-style-h3>Assembly procedure <heading-style-h3>
1. Check the condition of the anchor support and the cable.
2. Install 2 12, 14 or 16 mm cable clamps on a closed spindle or support cable.Position the 12 mm cable inside the aluminum matrix using the 6 M10 bolts. Tighten to a tightening torque of 50 Nm.
<heading-style-h3>Installation advice <heading-style-h3>
Check that the hook passes freely between the wall and the NEWVIA Pack.
Cable loops can be made identically to avoid a direct shock between the connectors and the NEWVIA Pack.
Attention: the hook must be able to pass freely.
The lifespan of the material depends on the quality of the support and the environment.
Deterioration may be increased in certain environments (snow, ice, falling rocks, etc.).
A minimum check every 12 months is required.